Nexans said on November 6 that it has signed a subcontract covering 420 km of a cable system for the Corinth–Kos electricity interconnection. The order forms part of a broader project to link the Dodecanese islands to mainland Greece.
Nexans puts the rating of the wider interconnection at 1 GW. It says the order will occupy production capacity into mid-2028, an indication of how far ahead large subsea electrical projects book manufacturing.