A 200 MW wind farm and a 200 MW data center use the same unit to describe quite different things. The wind farm’s rating describes what its turbines can produce under specified conditions. The data center’s figure might refer to electricity available to its servers or to a facility limit that includes cooling and other equipment.

Start at the meter

Campus plans should specify which load the number measures, what capacity arrives in the first phase and when the utility expects to deliver it. The IEA’s latest outlook describes delays in grid connections, transmission and equipment procurement as constraints on those schedules. [1]

Hourly wind output also matters. A contract for enough renewable energy over a year can leave long stretches when a campus draws on utility service, storage or another source of generation. That gap changes the size and cost of the power system a developer needs before construction.